MEPCO New Connection
Are you in search of a new MEPCO electricity connection? Let us assist you in the process. You can either visit the nearest office to obtain the application form, or you can opt for the online application.
You will encounter a straightforward form where you can select the type of electricity connection. In the Distribution Company list, be sure to choose MEPCO. Complete all other fields, upload scanned copies of the relevant documents, and proceed to apply for a new connection.
Procedure for Obtaining a New Connection
- Fill out the online application form [Click the link].
- Upload scanned copies of the following documents: (a) Proof of ownership. (b) Undertaking by the applicant. (c) Power of attorney in case of more than one owner. (d) No Objection Certificate (NOC) if the applicant is a tenant. (e) Attested copy of the applicant’s CNIC. (f) Attested copies of CNICs of two witnesses (not required for a single-phase connection). (g) A copy of the relevant tariff duly signed by the consumer.
- Submit the application form.
- Obtain a printed copy of the application form.
- Attach copies of all required documents to the application form.
- Send the application along with all attachments to the relevant office.
- After document verification, you will receive a demand notice.
- Pay the demand notice at the designated bank.
- Submit a copy of the paid demand notice to the relevant office.
- The meter connection will be installed after the verification of the paid demand notice.
If you have applied for a new connection and wish to check the application status, you can visit the nearest office or call the helpline. To check the MEPCO bill for your new connection,